The Tucznawa Solar Park project is one of the first projects being developed by our company. We started work on the project at the beginning of 2020, and the project achieved ready-to-build (RtB) status in early 2022.
Construction works began in mid-2023. The project is unique in its medium-voltage connection capacity (2 x 12.5 MW). The project uses efficient bifacial photovoltaic modules, which also produce electricity from rays reflected from the ground surface. The project is located next to the production facilities in the Tucznawa economic zone in Dąbrowa Górnicza.
Once constructed, the project will power approximately 6000 households.
Most important data:
Location: city of Dąbrowa Górnicza, Silesian voivodeship
Installed capacity: app. 25 MW
Production in first year: app. 27.5 GWh
Area: app. 29 ha
DSO: Tauron Dystrybucja
Status: under construction
Planned commissioning: Q3 2024