Wieluń Południe Solar Park has been developed by our company since mid-2021. It achieved ready-to-build (RtB) status in mid-2023. The project is located in the industrial part of the town of Wieluń – close to the Wielton plant, the municipal sewage treatment plant and next to the Wieluń-Wierszów railway. The point of connection to the grid is the MV switchgear in GPZ Wielun.
Once constructed, the project will power approximately 2000 households.
Most important data:
Location: City of Wieluń, Lodz Voivodship
Installed capacity: app. 6.9 MW
Production in first year: app. 7.59 GW
Area: app. 8 ha
DSO: PGE Dystrybucja
Status: RtB
Planned commissioning: end of 2025